Task 4: Impact Analysis
With this task, we want to find out what are the benefits for the using the stochastic model with recourse.
There are two quality metrics: the VVS and the EVPI
Expected Value of Perfect Information (EVPI)
- Individual determination of the best possible solution for each scenario
- Difference between the weighted average of the best possible solution for each scenario and the objective function value of the stochastic solution
- Interpretation: Maximum value that a decision-maker would be willing to pay in order to obtain complete information about the realisation of the uncertainty
Value of the Stochastic Solution (VSS)
- Comparison of the deterministic and stochastic solution
- Determination of the expected costs of the deterministic solution across all scenarios
- VSS: Difference between the objective function value of the stochastic solution and the weighted costs of the deterministic solution
- VSS=0 means that there is no advantage in taking uncertainty into account
- VSS>0 shows that the decisions can be adjusted in anticipation of the uncertainty so that the expected costs fall
Sub-Task 1: Implement a model that takes the result from the average run and set all investment decisions (y0) to the result vector, and then just optimises the rest of the core model.